华电技术 ›› 2014, Vol. 36 ›› Issue (2): 16-17.

• 专题综述 • 上一篇    下一篇

哈三电厂厂用电率偏高原因分析及处理

  

  1. (华电能源股份有限公司哈尔滨第三发电厂,哈尔滨〓150024)
  • 出版日期:2014-02-25

Treatment and case analysis of high power consumption rate in Harbin Third Power Plant

  1. (Harbin Third Power Plant of Huadian Energy Corporation Limited, Harbin 150024, China)
  • Published:2014-02-25

摘要: 摘要:以华电能源股份有限公司哈尔滨第三发电厂 #3机组为例,分析了厂用电率偏高的原因,论述了影响厂用电率的因素。采取针对性调整和技术改造措施后, #3机组厂用电率明显降低。

关键词: 关键词:厂用电率, 节能, 循环水泵, 炉水循环泵, 凝结水泵

Abstract: Abstract:Take #3 unit of Harbin Third Power Plant of Huadian Energy Corporation Limited as an example, the reason of high power consumption rate were analyzed,the influencing factor of power consumption rate were discussed. After take the measures of targeted adjustment and technical transformation, the power consumption rate of #3 unit were clear decreased.

Key words: Keywords:power consumption rate, energy conservation, circulating water pump, boiler water circulating pump, condensate pump