Huadian Technology ›› 2019, Vol. 41 ›› Issue (6): 72-75.

Previous Articles     Next Articles

Design and manufacture of FRP chimney liner in a coalfired power plant

  

  1. Beijing Datang Hengtong Technology Company Limited, Beijing 100097, China
  • Published:2019-06-25

Abstract:

Taking a cogeneration project of 2×350MW coalfired units as an example, the adaptability of FRP chimney liner in WESP flue gas chimneys of coalfired power plants is expounded. According to practical working condition,2 kinds of layers are designed and manufactured on site as FRP chimney liner.The pipe sections are sampled and tested for mechanical properties by a thirdparty testing agency. Comparison of raw material costs provide guidance for the layer design of the inner FRP chimney liner after wet desulfurization in thermal power plants.

Key words: