Optimal start up on 600MW steam turbine

  

  1. Hunan Huadian Changsha Power Generation Company Limited, Changsha 410203,China
  • Published:2016-07-25

Abstract:

Abstract:According to the status of Hunan Huadian Changsha Power Generation Company Limited,this paper adjusts allocation of turning time of turbine startup and startup parameters under a reasonable condition. In the process of implementation,mediumspeed warming has shortened from 4.0h to 2.5h,which improves warming efficiency and ongrid energy. Finally,this paper proposes a optimization measure which is to add cylinder drying device.